After the last trail run bumping over rocks & stumps I knew I needed a skid pan. Checking dimensions, I found that I had a piece of stainless that was close enough, so my skid pan is started.
I welded a cross brace at the front A arms.
The piece of SS was 17.5" X 70" so my plan was have it cut to at 64.5" and both long sides bent up 90 degrees 1 3/8". Then have small bends across the pan at 2" (down), 6.5" (up), 17" (up), 36" (up), the sides were cut to allow the bends. I also made a wire jig so the bender knew about what I was looking for.
The metal came back close to what I needed.
Then I started fitting under the Tracker to see where to notch for the cross members.
I had holes punched about where I thought they were need (on the sides so bolts would not get ground off) and then built brackets to hang the skid pan with. I am hanging it off my bumper with two bolts, the two bolts at back of A arms cross member, and two bolts at the transfer case member. I welded the nuts on the brackets so it would be easier installing removing.
Fitting, welding, grinding, (cutting off the bracket in wrong place) took longer then I figured, so hope to finish up tomorrow.
Replaced the bracket, enlarged some holes and bolted skid pan in place.
Test at Walker Valley on Sunday.